AC NEWS


Amarillo voters gave their go-ahead to a variety of projects and initiatives aimed at enhancing the Amarillo College landscape with passage of an $89.206 million bond referendum in the May 4, 2019 election.

Current Projects

Art Department Renovation

Art Department Reno Thumb

Plains Builders was selected as the Construction Manager contractor for this project and the basement is about 95% demolished as of April 20th.

Innovation
Outpost

Innovation Outpost Thumb

Western Builders (CMAR) is currently demolishing the interior of the structure and this project is currently under budget. 

Student Service
Center

SSC1 Thumb Revised March 2021

Dekker, Perich & Sabatini (DPS) – DPS met with the historical commission which resulted in some changes to the schematic design.

 

Carter Fitness Center

Carter Fitness Center Thumb

The committee met with Sim+ Architects to review the current design and approved the direction they were headed.

 

HVAC Infrastructure

HVAC Thumb

Sim+ Architects are 100% complete with Construction Documents and preparing a boiler plate for these bid documents.

First Responders Academy

First Responders Academy Thumb
Dekker, Perich & Sabatini (DPS) presented their schematic design to the committee and was approved. 

 

ADA Projects / Paving Projects

ADA / Paving Project Thumb

Connector Roads at West Campus are approximately 95% complete. The roads are open.